Complete Workover Rig Specifications Table (Standard Models)

The table below includes all key engineering parameters for our most requested models. Custom specs available on request.

Parameter SJW-90 SJW-150 SJW-200 SJW-250 SJW-300
Hook Load (lbs) 90,000 150,000 200,000 250,000 300,000
Hook Load (kN) 400 667 890 1,112 1,334
Max Depth (2-7/8" tubing, ft) 7,000 12,000 15,000 18,000 22,000
Mast Type 2-section telescopic 3-section telescopic 3-section telescopic 3-section telescopic 3-section heavy
Mast Extended Height (ft) 72 96 102 108 112
Mast Retracted Height (ft) 38 44 46 48 52
Clearance Under Mast (ft) 14 16 17 18 19
Drawworks Power (HP) 250 400 500 600 700
Line Pull (bare drum, lbs) 18,000 30,000 35,000 40,000 45,000
Wireline Diameter (in) 7/8 1 1-1/8 1-1/8 1-1/4
Drum Capacity (ft, 1" line) 4,500 6,000 7,000 8,000 9,000
Rotary Table Opening (in) 12 17.5 17.5 20.5 20.5
Power Source – Hydraulic (HP) 200 300 400 500 600
Power Source – Electric (kW) 150 250 350 450 N/A*
Fuel Tank (gal, hydraulic) 80 120 150 200 250
Transport Width (ft) 8.0 8.5 8.5 9.5** 10.5**
Max Module Weight (lbs) 18,000 25,000 28,000 35,000 40,000
Rig-up Time (hours, 4 crew) 8 12 16 20 24
Mast Raising Time (min) 15 20 25 30 35


Hydraulic vs Electric – Specification Comparison

For models offered in both drive types, here are the key differences:

Specification Hydraulic Version Electric Version (AC-VFD)
Power source Diesel engine (onboard) Grid or generator (480V/600V)
Fuel / energy consumption 8–12 gal/hour at full load 150–200 kWh/hour (approx 5–7 gal diesel equivalent)
Noise level (at 10m) 85–90 dBA 70–75 dBA
Speed control Hydraulic valve (manual or pilot) Digital – 0.1 ft/min increments
Regenerative braking No (waste heat) Yes – feeds power back
Best for Remote, no grid Offshore, urban, emissions-controlled
Weight added Baseline +10% (VFD cabinet, transformer)
Operating temperature range -20°C to +55°C -10°C to +50°C (cold kit available)

Snubbing Workover Rig Specifications (Integrated)

When adding snubbing capability, these additional specifications apply:

Snubbing Parameter SJW-150S SJW-200S SJW-250S
Snubbing jack pull/push (lbs) 100,000 150,000 200,000
Wellhead pressure rating (psi) 5,000 / 10,000 5,000 / 10,000 10,000
Stripper rubber size range (in) 1.0 – 3.5 1.0 – 4.5 1.5 – 5.0
Snubbing stroke length (ft) 10 10 12
Control console Remote hydraulic (50 ft hose) Remote hydraulic + digital Digital with data logging
Adds to rig height (ft) +6 +7 +8
Adds to weight (lbs) 6,000 8,000 10,000

Application-Specific Specification Guides

For Offshore Platform Workover

Specification Priority Minimum Requirement Our Typical
Corrosion protection Marine coating, stainless fittings 3-layer epoxy + zinc anodes
Deck loading (psf) Platform-specific Modular design – spread load
Crane lift capacity Each module < crane rating Max module 25,000 lbs (SJW-150)
Salt spray testing ASTM B117 >1,000 hrs 1,500 hrs

For Desert / High Ambient Temperature

Specification Priority Minimum Requirement Our Typical
Cooling system Radiator + hydraulic oil cooler Oversized coolers + fan reversal
Dust sealing IP54 minimum IP65 on control cabin
Solar radiation protection UV-stabilized hoses UV + heat-reflective paint
Operating temperature Up to 55°C Tested to 60°C

For Arctic / Low Temperature

Specification Priority Minimum Requirement Our Typical
Cold start assist Block heater + battery heater Full arctic package
Hydraulic fluid Synthetic, -40°C pour point Mobil SHC 500 series
Steel brittleness API 4F low-temp grade Charpy V-notch tested
Cabin heating Maintain 15°C at -40°C 20°C maintained

Product Types – By Specification Tier

We group our workover rigs into three specification tiers for easier selection:

Tier Models Hook Load Range Typical Applications Standard Delivery
Light SJW-90 90k lbs Shallow CBM, rod pump servicing, small operators 5–6 months
Medium SJW-150, SJW-200 150k – 200k lbs Most conventional workover, offshore platform, contractors 6–8 months
Heavy SJW-250, SJW-300 250k – 300k lbs Deep wells, heavy fishing, P&A, offshore large platforms 8–10 months

Why Choose SJ Petro for Your Workover Rig Specifications?

1. We Give You the Full Data Package – Not Just Marketing Numbers
We provide certified load test reports, dimensional CAD drawings, hydraulic schematics, and electrical single-line diagrams. No hidden specifications.

2. Every Spec Is Verified at Factory
Hook load is tested to 110% of rated. Mast deflection measured at full load. Cycle counts on hydraulic valves. You get a signed test report with each rig.

3. Custom Specifications Without Re-engineering Fees
Need a non-standard mast height? Different well center spacing? Higher snubbing pressure? We adjust our standard designs without charging custom engineering fees for reasonable changes.

4. Interchangeability Across Models
Many components (hydraulic pumps, control valves, wireline sheaves) are common across the SJW-150, -200, and -250 families. This reduces your spare parts inventory.

5. Digital Specifications – 3D Models Available
We can supply STEP or IGES models of the rig for your platform layout or pad design. Also available: rig-up animation videos showing module sequence.

6. 15-Year Spares Guarantee with Spec Traceability
Every part has a specification sheet and retains the same form, fit, and function for 15 years. No undocumented substitutions.

Frequently Asked Questions (FAQ)

Q1: How do I calculate which hook load I need for my well depth?
Use this rule of thumb: weight of tubing (lbs/ft) × depth (ft) + 20% safety margin. For 2-7/8" tubing (approx 6.5 lbs/ft) at 10,000 ft: 65,000 lbs + 20% = 78,000 lbs → SJW-150 (150k) is more than enough. For 3-1/2" tubing (9.3 lbs/ft) at 15,000 ft: 139,500 lbs + 20% = 167,400 lbs → need SJW-200 or -250.

Q2: What is the difference between "hook load” and "line pull”?
Hook load is the weight suspended from the traveling block (actual tubing weight). Line pull is the force at the drawworks drum before the block and tackle mechanical advantage. For a typical 6-line string-up, line pull ≈ hook load / 6 (minus friction).

Q3: Can I get a specification sheet in metric units (kN, meters, kg)?
Yes. All our standard spec sheets are available in both imperial and metric. Download from our website or request by email.

Q4: What transport dimensions matter most for road permits?
Height (retracted mast), width, and axle weights. Our SJW-150 truck-mounted is 13.5 ft height × 8.5 ft width – legal in most US states without permit. The SJW-250 skid modules exceed 9.5 ft width and require oversize permits.

Q5: How accurate are your rig-up time specifications?
Times assume a 4-person experienced crew, prepared pad, and no weather delays. First rig-up on a new site takes longer (add 50%). We provide a rig-up checklist to help you achieve the specified times.

Q6: Do your electric workover rig specifications include harmonic distortion limits?
Yes. Our AC-VFD drives meet IEEE 519 guidelines for harmonic distortion (<5% THD). We can provide harmonic analysis for your site’s power quality requirements.

Q7: Can I get a certified load test at your factory before shipment?
Absolutely. We schedule witness testing upon request. You will see the rig pull 110% of rated hook load with calibrated load cells. Test report stamped by our QA manager.

Q8: How do I interpret "clearance under mast”?
This is the vertical distance from the rig floor to the bottom of the mast when raised. It must accommodate your BOP stack, wellhead, and any lubricator. For example, a 10,000 psi BOP stack with dual rams is about 8–10 ft tall – you need at least 14 ft clearance (our SJW-150 has 16 ft).

Q9: Do you provide specifications for explosion-proof electricals (Class I, Div 1)?
Yes. For onshore hazardous areas, we can supply XP enclosures, sealed conduits, and intrinsic safety barriers. Additional cost and lead time (2–3 months). Full specification available on request.

Q10: How do I request a custom specification quote?
Fill out our Workover Rig Spec Request Form with: well depth, tubing size, desired hook load, any special conditions (H2S, temperature, offshore), and preferred drive. Our engineering team responds within 3 business days with a preliminary spec sheet and budget price.